Expected annual
$1.7M
One-time setup
$1.9M
Annual recurring
$1.7M
Personnel
9
Initial capital outlay is approximately $1,855,000 driven by site/bridge work, power/vehicles, and research reserves; ongoing annual operations are about $1,652,000 driven primarily by 24/7 security staffing, medevac/contingency funds, and recurring research/monitoring.
One-Time Capital Costs
Total: $1.9M
Annual Recurring Costs
Total: $1.7M/yr
Cost Scenarios
📊
Baseline
(baseline)
$1.7M/yr
Normal uneventful year with routine operations and no major incidents.
routine_operations
daily_teatime_and_monitoring
🚨
Minor Incident
$1.7M/yr
A single personnel injury or small civilian exposure requiring medevac, limited repairs, amnestic use, and minor legal/cover response.
personnel_injury
single_civilian_incident
small_equipment_damage
🚨
Major Breach
$2.5M/yr
Significant containment breach or infrastructure failure (bridge collapse, mass exposure) requiring major repairs, legal settlements, emergency response, and temporary scale-up of staff.
bridge_collapses
mass_exposure
major_property_damage
Personnel
9 total
| Role | Count | Notes |
|---|---|---|
| Security Officer / MTF Agent | 6 | [#4] 2 guards per shift × 3 shifts to provide 24/7 manning. |
| Site Manager / Administrative Staff | 1 | [#4] On-site manager to coordinate operations and local liaison. |
| Medical Officer | 1 | [#4, #6] Medic/first responder on rotation; coordinates with medevac contracts. |
| Engineer / Maintenance | 1 | [#4, #7, #8] Maintenance/driver for site upkeep, generator/solar upkeep and vehicle/boat maintenance. |
Confidence Notes
Estimates are based on analyst-provided ranges and typical Foundation unit costs; many line items have rough ranges and contingency choices (e.g., long-term reserve) so totals have moderate uncertainty.