SCP-2825
Euclid
~
medium confidence
SCP-2825
Expected annual
$6.9M
One-time setup
$78.7M
Annual recurring
$6.6M
Personnel
42
Initial capital/setup (land acquisition, perimeter, observation post, lab and specialized equipment) dominates one-time costs (~$78.7M total incl. extreme engineering contingency); recurring operations (staff, research, maintenance, logistics) are the main annual drivers (~$6.59M/yr).
One-Time Capital Costs
Total: $78.7M
Annual Recurring Costs
Total: $6.6M/yr
Cost Scenarios
📊
Baseline
(baseline)
$6.6M/yr
Normal operational year with no major incidents; routine monitoring, research, containment and maintenance proceed as expected.
no_breach
normal_research_activity
routine_maintenance
🚨
Minor Incident
$7.1M/yr
Localized containment breach or medical/environmental incident requiring emergency response, repairs, overtime and limited remediation.
small_breach
equipment_failure
localized_spread_of_contaminant
🚨
Major Breach
$9.1M/yr
Significant containment failure or large-scale ecological impact requiring major remediation, extended deployment of personnel, legal action and infrastructure repair.
large_scale_breach
widespread_environmental_damage
major_equipment_loss
🚨
Extreme Containment Engineering
$56.6M/yr
Decision to undertake large-scale containment/neutralization engineering (dams, diversion channels, mass neutralizers) and associated emergency construction in response to uncontrolled spread or policy decision.
policy_decision_to_engineer
catastrophic_spread
unmanageable_environmental_risk
Personnel
42 total
| Role | Count | Notes |
|---|---|---|
| Security Officer / MTF Agent | 18 | [#4] 24/7 perimeter staffing estimate (midpoint of 12–24 personnel); includes patrols, supervisors and boat/ATV crews. |
| Research Scientist | 10 | [#5] Ecologists, molecular biologists, behavioral specialists and field researchers (midpoint of 8–12 specialists). |
| Field Technician (Drone/ROV/Boat Operator) | 6 | [#6, #8, #15] Operators and technicians to run UAVs/ROVs/vessels and maintain vehicles/equipment; headcount inferred from equipment fleet and operational tempo. |
| Veterinary Officer / Animal Technician | 4 | [#17, #18] On-call vets and animal technicians for capture, quarantine and ongoing care (staffing component of #18 included in wages). |
| Site Operations / Observation Post Staff | 4 | [#3, #30] Site ops, comms, admin and support staff for Observation Post 30 and daily facility operations. |
Confidence Notes
Analyst notes provide detailed line-item ranges allowing midpoint-based estimates, but significant uncertainties remain (large ranges per item, potential regional cost variation, and an open-ended extreme-containment cost). Confidence rated medium for reasonable bounding but nontrivial tail-risk.