SCP-6022
Euclid
~
medium confidence
SCP-6022
Expected annual
$16.3M
One-time setup
$67.3M
Annual recurring
$15.5M
Personnel
72
Estimated one-time capital costs are approximately $67.3M driven by site build, emergency stockpiles, land acquisition and a large contingency reserve; ongoing annual costs are approximately $15.53M driven primarily by staff wages, BSL‑4 access / research, logistics and cover-story/liaison operations.
One-Time Capital Costs
Total: $67.3M
Annual Recurring Costs
Total: $15.5M/yr
Cost Scenarios
📊
Baseline
(baseline)
$15.5M/yr
Normal operational year with no major incident; routine patrols, monitoring, training, and replenishment.
no SCP-6022-4 amplitude exceedance
routine patrols and monitoring only
🚨
Minor Incident
$16.3M/yr
Localized SCP-6022-2 or SCP-6022-3 incident requiring quarantine, medical care, incineration and additional legal/cover operations.
single driver exposure (SCP-6022-2) with infection/quarantine
small-scale incineration and prosthetic/cover payouts
🚨
Major Breach
$20.5M/yr
A SCP-6022-4 event requiring enactment of Procedure 6022-Thysia, broad incineration/quarantine, mass amnestics and significant remedial action.
SCP-6022-4 amplitude exceedance >20m
enactment of Procedure 6022-Thysia and multi-unit response
🚨
Catastrophic Breach
$50.5M/yr
Large-amplitude SCP-6022-4 activation with cascading catastrophic effects (national-level response, mass remediation, drawing contingency reserve).
extreme SCP-6022-4 activation
failure/delay of Procedure 6022-Thysia, large-scale secondary disasters
Personnel
72 total
| Role | Count | Notes |
|---|---|---|
| Security Officer / MTF Agent | 42 | 36 active patrol operators plus 6 backup/maintenance staff for 24/7 perimeter patrols; hazard pay included in staff_wages. [#1] |
| Site Security / Guards | 13 | On-site guards included in the 24/7 staffing complement at Site-6022. [#3] |
| Research Scientist | 4 | Field researchers and laboratory staff for monitoring and small-scale R&D. [#3, #22] |
| Medical Officer | 2 | On-site medics for immediate care and amnestic administration. [#3, #10] |
| Engineer / Maintenance | 6 | Maintenance staff for vehicles, generators, sensors, and site infrastructure. [#1, #2, #13] |
| Administrative Staff | 4 | Site manager, admin and liaison personnel handling documentation, cover stories and coordination. [#3, #17] |
| Site Director / Executive Staff | 1 | Site manager / senior on-site executive. [#3] |
Confidence Notes
Analyst notes provide detailed line items and ranges but many costs depend on policy choices (land acquisition vs. government buy-in, building vs. leasing BSL-4, size of contingency reserves) and on the anomaly's unpredictable activation frequency; therefore estimates are moderately confident but could vary widely.