SCP-7862
Euclid
~
medium confidence
SCP-7862
Expected annual
$2.1M
One-time setup
$2.2M
Annual recurring
$2.1M
Personnel
18
Initial one-time capital costs are roughly $2.16M driven by land, perimeter and facility construction plus lab and vehicles; ongoing annual costs are roughly $2.10M driven primarily by staff wages (security + scientific/site staff), food provisioning, testing/monitoring and contingency reserves.
One-Time Capital Costs
Total: $2.2M
Annual Recurring Costs
Total: $2.1M/yr
Cost Scenarios
📊
Baseline
(baseline)
$2.1M/yr
Normal year with routine operations and no major incidents.
no breaches
routine testing and maintenance
🚨
Minor Incident
$2.2M/yr
Small containment/policy breach or isolated dietary noncompliance requiring quarantine and extra testing.
single-staff dietary breach
localized contamination
small emergency quarantine
🚨
Major Breach
$2.6M/yr
Larger breach requiring extended medical response, emergency repairs, public-relations/legal action and expanded containment upgrades.
multiple-staff contamination
structural damage to containment
evidence leak requiring legal/PR remediation
Personnel
18 total
| Role | Count | Notes |
|---|---|---|
| Security Officer / MTF Agent | 10 | [#7] 24/7 guard rotation to cover shifts (8–12 guards in analyst notes); count chosen to provide continuous coverage with supervisors and redundancy. |
| Site Director / Executive Staff | 1 | [#8] Senior manager responsible for operations and liaison. |
| Research Scientist | 2 | [#8] On-site researchers to run analyses and experiments; aligns with analyst note of 2–4 researchers. |
| Technician / Lab Technician | 2 | [#8, #20] Technicians for sample processing, instrument operation and lab support. |
| Engineer / Maintenance | 1 | [#6, #24] Site maintenance and equipment/vehicle upkeep. |
| Medical Officer / Nutritionist | 1 | [#17] Medical surveillance and nutrition support for vegan staff. |
| Administrative Staff | 1 | [#8, #13] HR/administration handling screening, scheduling, and recordkeeping. |
Confidence Notes
Mid-range estimates used for line items with wide geographic and scope variability; costs for land, facility construction and lab capability are location-dependent and ranges provided in analyst notes are broad, so confidence is medium.