Expected annual
$714K
One-time setup
$1.2M
Annual recurring
$709K
Personnel
7
Upfront capital for a custom angled magnetic suspension, room retrofit, and integrated monitoring is the main driver (~$1.23M one-time); recurring costs are dominated by staff (containment, security, research) and ongoing contingency, yielding ~ $709k/year.
One-Time Capital Costs
Total: $1.2M
Annual Recurring Costs
Total: $709K/yr
Cost Scenarios
📊
Baseline
(baseline)
$709K/yr
Routine year with no major activations; containment maintained, scheduled maintenance and research proceed as normal.
no activations
regular maintenance
planned research activity
🚨
Minor Incident
$744K/yr
A localized activation or small containment hardware failure requiring sensor replacements, limited repairs, cleanup, and short downtime.
small activation (4‑minute effect) causing sensor damage
locker rendered temporarily inoperable
minor fire/smoke cleanup
🚨
Major Incident
$1.0M/yr
Significant activation (fire, structural damage, contamination or repeated activations) requiring major repairs, equipment replacement, extended research interruption and possible contractor remediation.
full room fire/thermal event
structural damage or contamination
multiple activations or catastrophic equipment loss
Personnel
7 total
| Role | Count | Notes |
|---|---|---|
| Containment Technician | 1 | [#9, #11] Full‑time trained technician responsible for daily assessments, maintenance, inspections and documentation. |
| Security Officer / MTF Agent | 3 | [#10] On‑site security coverage (shifted staffing to cover 24/7) included in security budget. |
| Site Supervisor / On‑call Containment Supervisor | 1 | [#10] On‑call supervisory stipend and immediate notification responsibilities if locker is inoperable. |
| Research Scientist (PI) | 1 | [#24, #13, #14] Part‑time/full‑time PI responsible for coordinating imaging and invasive sampling projects. |
| Research Technician / Data Analyst | 1 | [#24, #13] Technician(s) to run imaging, process data, and support experiments. |
Confidence Notes
Estimates derived from analyst ranges using midpoints and conservative contingency assumptions. Line‑item costs are relatively well described but incident frequencies and site‑specific marginal costs (existing infrastructure vs full buildout) are uncertain, hence medium confidence.