SCP-671
Expected annual
$749K
One-time setup
$1.9M
Annual recurring
$744K
Personnel
9
Initial setup is moderately expensive ($~1.86M one-time) driven by bespoke heat-welded terrarium construction, room remodeling/airlock installation, and a large contingency reserve; recurring costs (~$744k/yr) are dominated by staffing, maintenance, insurance, consumables, and ongoing research/monitoring.
One-Time Capital Costs
Total: $1.9M
Annual Recurring Costs
Total: $744K/yr
Cost Scenarios
📊
Baseline
(baseline)
$744K/yr
Normal uneventful year with routine operations, maintenance, and research activity.
no escapes
planned maintenance
routine research
🚨
Minor Incident
$769K/yr
Small escape or localized disassembly event requiring targeted remediation and short-term repairs/overtime.
localized escape
minor equipment disassembly
emergency insecticide deployment
🚨
Major Breach
$894K/yr
Significant containment breach causing loss of specialized equipment or room infrastructure and requiring replacement and extended downtime.
breach of terrarium/airlock
loss of monitoring equipment
extended repairs
🚨
Catastrophic Breach
$1.7M/yr
Large-scale escape causing structural damage or widespread disassembly of facility systems, triggering use of contingency funds and reconstruction.
uncontained colony spread
disassembly of critical infrastructure
multi-system failure
Personnel
9 total
| Role | Count | Notes |
|---|---|---|
| Research Scientist | 2 | [#13] Lead researchers to run experiments and manage behavior studies. |
| Technician | 2 | [#13] Technicians for day-to-day maintenance, substrate handling, and equipment upkeep. |
| Monitoring Operator | 2 | [#13] Camera/monitor operators and data logging personnel (positions may be combined with technicians). |
| Security Officer / MTF Agent | 2 | [#13] Dedicated security personnel for site/room access control and emergency response. |
| Facility Manager / Administrative Staff | 1 | [#13, #25] Site manager responsible for compliance, scheduling, procurement, and coordination. |
Confidence Notes
Midpoint estimates used across wide ranges in analyst notes; staffing and consumable costs are reasonably bounded but one-time fabrication and breach probabilities are uncertain, so overall confidence is medium.